How long does it take to get a permit approved?

Site Plan

Please allow 15 business days from time site plan application is accepted for review for any comments or permit to be issued.  

New Commercial Building

Please allow 15 business days from time building application is accepted for review for any comments or permit to be issue.

A New Commercial Building Permit Application can be submitted only after the Site Plan Application has been submitted and the first set of comments have been issued.

Commercial Remodel

Please allow 15 business days from time building application is accepted for review for any comments or permit to be issued.

New Residential

Please allow 10 to 15 business days from time building application is accepted for review for any comments or permit to be issued.

Basic Repairs (Water Heater Replacement, HVAC Change out)

Permit approval will take approximately 10-15 business days.

Irrigation & Water Softener Install

Permit approval will take approximately 10-15 business days.

Patio / Patio Cover

Permit approval will take approximately 10-15 business days .

Show All Answers

1. When do I need a permit?
2. How long does it take to get a permit approved?
3. How much is a permit?
4. Do I need a permit for a flag pole at my home or business?
5. Do I need a permit for a Generator ?
6. Do I need a permit for a Garage Sale?